30.

AA and BB together can do a job in 22 days; BB and CC can do it in four days; and AA and CC in 2252\dfrac25 days. The number of days required for AA to do the job alone is:
11
33
66
1212
2.82.8
Answer: B
Concepts:ratesystem of equations
Small hint:
Let a,b,ca,b,c be the fractions of the job completed per day
Big hint:
Add a+b=12a+b=\frac{1}{2} and a+c=512a+c=\frac{5}{12}, then subtract b+c=14b+c=\frac{1}{4}
Solution:
Let a,b,ca,b,c be the individual daily rates. Then a+b=12,b+c=14,a+c=512. \begin{aligned} a+b&=\frac12,\\ b+c&=\frac14,\\ a+c&=\frac5{12}. \end{aligned} Thus 2a=(a+b)+(a+c)−(b+c)=12+512−14=23, \begin{aligned} 2a&=(a+b)+(a+c)\\ &\quad{}-(b+c)\\ &=\frac12+\frac5{12}-\frac14\\ &=\frac23, \end{aligned} so a=13.a=\frac{1}{3}. Therefore AA needs 33 days.
Thus, the correct answer is B.
LIVE by Po-Shen Loh
Programs

LIVE Classes

Self-Paced Classes

Stars

Scholarship

About Us

Who Is Po-Shen Loh?

Email Contact

Newsletter

Jobs

Become a Star

For a more Thought Full world.

© 2026 Expii, Inc.